11-15-23 Beach Nourishment Project Updates

PHASE 5
Operations will resume November 16, 2023 as scheduled.  Trucks will be entering the Gray Street beach access and will start placing sand at the Surf City line and continue approximately 3,200 feet North of the Town line. The Contractor will pause operations for the Thanksgiving holiday on November 23rd and November 24th.   At the close of last season, we placed 410,905 Cubic Yards of sand and expect to place an additional 225,095 Cubic Yards of sand that is expected to be completed in February 2024!  The contractor will be pausing for Thanksgiving on Thursday and Friday.
PHASE 1
The Town’s permit modification to request a November 1st start date was denied.  The Town’s contractor is preparing to start November 27th.  Sand will be placed just South of Topsail Reef Villas and continue South towards Oceans Edge Restaurant at the St. Regis.